Champion Environmental Services, Inc. was awarded the hazardous material abatement, building demolition, and site clearance for Phase II at the Westlawn Housing Development in Milwaukee, WI.
The project involves 29 multiunit buildings. The initial phase will be dedicated to the abatement of asbestos containing floor tile/mastic, fittings on fiberglass insulation, transite panels, window caulk, paper duct wrap, and sink undercoating.
After the apartments are properly abated and receive final air clearances, the demolition crew will proceed with wrecking the units. Champion Environmental Services, Inc. anticipates a recycling rate of nearly 97%.
This effort is part of a larger initiative by The Wisconsin Housing and Economic Development Authority (WHEDA). According to a press release by WHEDA on December 3, 2010, the project will evolve into “ . . .the North End - Phase 2 development to construct two, five-story apartment buildings totaling 155 units of rental housing. The program requires the property to set aside 20% of its units for low and moderate income residents. Specifically, 31 apartment units in North End - Phase 2 will be set aside for households at or below 60% of Milwaukee's County Median Income”.
Phase I of Westlawn was recently completed by Champion Environmental Services, Inc.
Showing posts with label demolition during winter. Show all posts
Showing posts with label demolition during winter. Show all posts
Thursday, December 9, 2010
Tuesday, December 7, 2010
Milwaukee Smokestack




This morning, in an unforgiveable subzero wind chill, Champion Environmental Services, Inc. mobilized to start the controlled dismantlement of 186’ smokestack. The proximity of key buildings, nearby rail lines, and above ground industrial service pipes dictated that we rig a robotic Brokk to a crane and work our way down in a top to bottom fashion.
Aggressive winter wind proved frustrating for the crane operator, yet, in time, we were able to sequence an approach that clipped the pace to an appropriate tempo.
The succession of pictures is the raising of the Brokk into place and subsequent production within a half hour. If the winds cooperate, the stack will be down in five working days.
Tuesday, January 5, 2010
Friday, December 18, 2009
Winter Weather and Demolition
Our office has been receiving phone inquires over the past few weeks with regard to performing demolition during the winter months. The main question is, “do you guys work throughout the winter”? The follow up question is a simple “how”?
The first question is easy to respond to, yes; we embody a 365 – 24/7 mode of operation. That being said, there is extensive criteria that allows Champion Environmental Services, Inc. to maintain an industrious pace during wintery conditions. What follows is a cursory overview of how Champion Environmental Services, Inc. functions in unfavorable environs.
While most operations surrounding construction tend to slow during cold the weather months, advances in technology and safe guideline practices – tempered with experience, allows Champion Environmental Services, Inc. to perform demolition despite low temperatures and adverse conditions.
In general, working outside in cold temperatures equates with slow work and more frequent breaks. Champion Environmental Services, Inc. hedges against this assumption through proactive strategic planning that is job/site specific. Our workforce of operators, laborers, project managers, and filed superintendents are fitted with the finest cold weather construction gear which is comprised of warm, breathable materials that is conducive to safe, productive work. Additionally, project managers and field superintendents continually monitor weather and site conditions to determine a sensible approach to the task at hand.
So “how” do we get demolition done with snow on the ground or in icy conditions?
It is imperative that all the workers survey the site prior to starting operations to identify potential road blocks/challenges which may inhibit work or create hazardous situations. Attention to detail, however small or insignificant in appearance, must be noted. A laborer picking bricks who is unaware of a small patch of ice could easily loose his/her footing while sorting/stacking piles and slip. A fall on the sidewalk outside your house is bad enough, but falling on a construction site with debris scattered or while carrying heavy equipment could be serious, or worse, potentially deadly.
As I have noted before, a clean-operable site which utilizes a material segregation plan affords greater efficiency. A winter environment dictates that we sometimes, albeit briefly, use machines to move snow so that pathways are clear to get trucks in/out and keep areas open to separate recyclable items.
Dust suppression during demolition is a delicate issue to address. Freezing temperatures means freezing water; an encrusted citadel would preclude safe operations on any level. Experienced machine operators must be selective while razing a structure. A careful approach can mitigate dust – snowfall can be a beneficial, added deterrent to particulate disbursement.
Ultimately, weather does not determine our ability function, safety drives the decision making process.
The first question is easy to respond to, yes; we embody a 365 – 24/7 mode of operation. That being said, there is extensive criteria that allows Champion Environmental Services, Inc. to maintain an industrious pace during wintery conditions. What follows is a cursory overview of how Champion Environmental Services, Inc. functions in unfavorable environs.
While most operations surrounding construction tend to slow during cold the weather months, advances in technology and safe guideline practices – tempered with experience, allows Champion Environmental Services, Inc. to perform demolition despite low temperatures and adverse conditions.
In general, working outside in cold temperatures equates with slow work and more frequent breaks. Champion Environmental Services, Inc. hedges against this assumption through proactive strategic planning that is job/site specific. Our workforce of operators, laborers, project managers, and filed superintendents are fitted with the finest cold weather construction gear which is comprised of warm, breathable materials that is conducive to safe, productive work. Additionally, project managers and field superintendents continually monitor weather and site conditions to determine a sensible approach to the task at hand.
So “how” do we get demolition done with snow on the ground or in icy conditions?
It is imperative that all the workers survey the site prior to starting operations to identify potential road blocks/challenges which may inhibit work or create hazardous situations. Attention to detail, however small or insignificant in appearance, must be noted. A laborer picking bricks who is unaware of a small patch of ice could easily loose his/her footing while sorting/stacking piles and slip. A fall on the sidewalk outside your house is bad enough, but falling on a construction site with debris scattered or while carrying heavy equipment could be serious, or worse, potentially deadly.
As I have noted before, a clean-operable site which utilizes a material segregation plan affords greater efficiency. A winter environment dictates that we sometimes, albeit briefly, use machines to move snow so that pathways are clear to get trucks in/out and keep areas open to separate recyclable items.
Dust suppression during demolition is a delicate issue to address. Freezing temperatures means freezing water; an encrusted citadel would preclude safe operations on any level. Experienced machine operators must be selective while razing a structure. A careful approach can mitigate dust – snowfall can be a beneficial, added deterrent to particulate disbursement.
Ultimately, weather does not determine our ability function, safety drives the decision making process.