The insanity continues - bid results just into our office. The scope here is an extensive amount of ACM pipe and associated fittings. While 85% of the abatement is readily exposed, some selective demolition is involved to reach part of the chases. An additional quantity of ACM floor mastic rounds the project.

Despite the public nature of these bid results, I still feel it is of little value to debase a competitor by naming each company here.

$77,550
$71,100
$63,550
$58,850
$43,820
$36,641

The numbers, particularly the low bid at $36,641, reflects troubled insensibility that has polluted our industry.