Progress At Wonder Lake Water Tower

Significant progress has been made on the deconstruction of the Wonder Lake water tower. Mobilization began on Wednesday, October 13. Prior to being on site, Champion Environmental Services, Inc. conducted a job specific safety assessment to ensure the protection of our workers as well as the neighboring properties.

Constant communication is relayed via radio communication between the laborers performing the torch work, the crane operator, and field superintendent. Daily toolbox meetings are conducted in order to determine what portions of the tower will be dismantled, review safety protocol, and discuss progress.

The local fire department visited the job site to inspect our operations; an additional random safety audit was conducted by our insurance carrier on the second day of work – both entities were fully confident with our approach to this project.

The field team assembled for this project has extensive experience. Each day ends with a debriefing of what went well, each team members responsibility going forward, and a review of what work will take place the next day.









No comments:

Post a Comment